Case Study

Davit Arms

Challenge

Our client needed to install scaffolding to completely replace crane rails above 5 bunkers at their energy from waste facility. This scaffolding could only be installed during a 3 day working window, and would have required a costly and time consuming hanging scaffold.

Action

Working with the client, a design was agreed to provide a permanent installation of a support system that could be erected before the shutdown and hinged into position only when required

Result

110 davits successfully fabricated, load tested to 5 times the working load and installed to meet shut down timescales. Easy access now available when required.